← GATE CSE 2012
Questions

Q31

MCQ2 marks, −0.67Operating systemsMedium

Consider the 33 processes, P1,P2P1, P2 and P3P3 shown in the table.

ProcessArrival TimeTime Units RequiredP105P217P334\small \begin{array}{|c|c|c|} \hline \textbf{Process} & \textbf{Arrival Time} & \textbf{Time Units Required} \\\hline \text{P1} & 0 & 5\\\hline \text{P2} & 1 & 7 \\\hline \text{P3} & 3 & 4 \\\hline \end{array}

The completion order of the 33 processes under the policies FCFS and RR22 (round robin scheduling with CPU quantum of 22 time units) are